SOUTH WAZIRISTAN LOWER: The Water and Power Development Authority (Wapda) has restored the affected generating units of the Gomal Zam Hydropower Station after eight years and successfully synchronised it with the national grid, bringing the facility back to its full generation capacity of 17.4 megawatts (MW). Officials said that both of the station’s generating units had ceased operations in October 2016 due to a major technical fault. One unit was repaired and brought back into service in June 2018, restoring half of the station’s installed capacity.